Bond construction update

We’re in the final phase of bond construction, and most of the projects scheduled for summer have been completed. However, there are still some major renovations and new additions in progress which may not be completed before the start of school. None of the ongoing construction will interfere with instruction or daily operations, but there may be some impact to drop off/pick up procedures and access to some areas of the school will be limited.  We appreciate your patience as we finalize building updates. 

See below for the current status of construction at your school as of Aug. 7.

Garland HS

  • Fine arts renovations for choir are scheduled for completion by Aug. 9. The new band hall addition is on schedule for completion by Nov. 1.
  • Melhart cabinets for music instrument storage are scheduled for delivery in January. Temporary storage will be used until the new cabinets arrive.
  • Temporary doors are in place for the fine arts renovation area. New doors are scheduled to arrive in mid-October.
  • The rear parking lot is not available per the construction plan. It will support the new addition.

 Webb MS

  • Melhart cabinets for music instrument storage are scheduled for delivery in December. Temporary storage has been installed.

 Schrade MS

  • Kilns are not available for use while the architect and contractor work to resolve the clearance issue of both kiln units in a small space.

 O’Banion MS

  • Construction will continue past the start of school on the security vestibule/entryway, new administration area and new fine arts addition. 

Centerville ES

  • Architect and engineer are working to develop a design solution for the front canopy and front entry sidewalk per ADA requirements. 
  • Temporary HVAC ductwork has been installed in cafetorium.

Hudson MS

  • Melhart cabinets for music instrument storage are scheduled for delivery in October. Temporary storage has been installed.

 Keeley ES

  • Work by ATMOS contractor has created open trenches as the east drive. Precautions should be taken when walking to school.

North Garland HS

  • Construction storage (laydown yard) for new fine arts addition will impact the student parking lot.
  • Contractor installation of new doors and hardware will continue through the school year.

South Garland HS

  • Construction storage (laydown yard) for new fine arts addition will impact the student parking lot.

Coyle MS

  • Construction storage (laydown yard) for new fine arts addition will impact the student parking lot.

Walnut Glen ES

  • Repairs to the kitchen sewer line are not part of the bond package. These will be addressed at a later time. Back-ups to the line and smells may be possible until this is resolved.

Sachse HS

  • Melhart cabinets for music instrument storage are scheduled for delivery in January. Temporary storage has been installed.

Jackson MS

  • Melhart cabinets for music instrument storage are scheduled for delivery in December. Temporary storage has been installed.

Lyles MS

  • Melhart cabinets for music instrument storage are scheduled for delivery in October. Temporary storage has been installed.